Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
ASX: AR3 | MARKET ANNOUNCEMENT ASX Release: 31 July 2026
Quarterly Activities Report
For the period of three months ending 30 June 2026
Highlights
Landmark quarter for Koppamurra: Pre-Feasibility Study and maiden Ore Reserve delivered
• Pre-Feasibility Study (PFS) and maiden Ore Reserve confirm Koppamurra as one of Australia's most advanced
ionic clay rare earths development projects: post-tax NPV8 of A$858 million, post-tax IRR of 99% and payback
of just 0.9 years , on initial capital expenditure of only A$178 million (refer ASX announcement "Pre-Feasibility
Study and maiden Ore Reserve confirm Koppamurra as a compelling project" 25 June 2026).
• Low-capital, low-complexity development pathway: shallow open-pit mining, a proven heap leach flowsheet
and rapid progressive rehabilitation underpin the Project's low technical risk and strong capital efficiency.
• Maiden Ore Reserve of 26 Mt @ 920 ppm Total Rare Earth Oxide (TREO) established — approximately 22%
higher grade than the global Mineral Resource average — providing a high value starting point for development
(refer ASX announcement "Maiden Ore Reserve positions Koppamurra for development" 25 June 2026).
• Updated global Mineral Resource of 243 Mt @ 751 ppm TREO, an increase of ~7 Mt versus the September 2024
estimate without additional drilling, reflecting improved geological modelling and resource interpretation.
• High-value product basket: average annual production of ~1,860 tonnes TREO, including the magnet rare earths
neodymium, praseodymium, dysprosium and terbium, together with yttrium, gadolinium, samarium and
lutetium — all increasingly critical to Western supply chains and subject to China's expanded export controls.
• Mining Lease Application preparation remains on track for submission in 2026.
ANSTO pilot-scale facility officially opened; Koppamurra pilot processing advancing
• Federal Government officially opened ANSTO's new critical minerals piloting facility in Sydney during the
quarter, with AR3 being the first industry partner to utilise the facility (refer ASX announcement "ANSTO's new
critical minerals facilities opened" 13 May 2026).
• ~30 tonnes of Koppamurra ore delivered to ANSTO's Sydney facility and prepared for processing, with pilot-
scale operations targeting commencement in August 2026 to produce Mixed Rare Earth Oxide (MREO) product
samples for customer qualification and offtake engagement.
• Pilot program co-funded under AR3's $5 million Australian Government International Partnerships in Critical
Minerals (IPCM) grant.
Overland Project — Discovery of Niobium-Rare Earth Carbonatite System identified
• Drilling has identified a niobium–rare earth carbonatite mineral system at Overland; a style of mineralisation
globally recognised as a major source of both Rare Earth Elements and niobium, both critical minerals with
strong demand (refer ASX announcement subsequent to the quarter end “Discovery of Niobium-Rare
Earth Carbonatite System identified at Overland Project” 8 July 2026). Follow up geophysics and drilling
is planned.
• Drilling at Overland comprising 22 aircore holes for 1,280 metres was completed across April and May 2026, to
test the Western Flank Zone and Basal Sandy Unit sedimentary-hosted uranium targets defined during the
March 2026 quarter (refer ASX announcement "AR3 commences uranium drilling at Overland, South Australia"
29 April 2026).
Corporate
• Cash position as at 30 June 2026: $4.6 million with an additional $2.1 million Australian Government
International Partnerships in Critical Minerals grant instalment expected to be received in August 2026.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
• A General Meeting (GM) of shareholders was held on 21 April 2026 to seek shareholder ratification of
placement shares and approval for the issuance of options attached to the January 2026 placement. All
resolutions put to the meeting were approved by shareholders.
• Engage with this announcement at the AR3 investor hub.
Managing Director’s Comments:
“This has been a landmark quarter for Australian Rare Earths. The delivery of our Pre-Feasibility Study and maiden Ore
Reserve for Koppamurra (with an after-tax NPV of A$858 million, a 99% IRR and payback of under a year on just A$178
million of initial capital) confirms this as one of the most compelling rare earth development opportunities in Australia
today.
Recent developments in global rare earth trade policy, together with the growing focus on supply-chain security and
diversification, have reinforced the strategic importance of Koppamurra. The project’s MREO basket, with a strong
weighting toward magnet and heavy rare earths, is well aligned with prospective demand from customers seeking secure
and reliable sources of supply outside China.
The quarter also saw the official opening of ANSTO's new critical minerals piloting facility in Sydney, where AR3 is the
first industry partner, with our ore on-site and pilot-scale processing commencing in August 2026.
At Overland, the identification of a new niobium-rare earths carbonatite mineral system represents a very exciting new
exploration opportunity for AR3.
With the PFS and Ore Reserve now delivered, our focus turns to the Pilot scale operations at ANSTO, our Mining Lease
Application, delivering product samples to potential customers and advancing offtake, project funding discussions
and completion of the Definitive Feasibility Study in 2027, as we work toward a final investment decision.”
Travis Beinke, Managing Director and CEO, Australian Rare Earths Limited
Australian Rare Earths Limited (AR3 or the Company) is pleased to provide an update on progress made during the
quarter ended 30 June 2026. The quarter was defined by the delivery of the Pre-Feasibility Study (PFS) and maiden Ore
Reserve for the Koppamurra Rare Earths Project, the official opening of ANSTO's new critical minerals piloting facility in
Sydney, and the identification of a new niobium-rare earths carbonatite mineral system at the Overland Project.
Operational Review
Koppamurra Rare Earths Project, South Australia
AR3 delivered a series of major milestones at the Koppamurra Rare Earths Project during the June quarter, culminating
in the release of the Project's Pre-Feasibility Study (PFS) and maiden Ore Reserve, alongside continued progress toward
pilot-scale processing and Mining Lease Application.
Pre-Feasibility Study and Maiden Ore Reserve Confirm Koppamurra as a Compelling Project
On 25 June 2026, AR3 released the results of the Pre-Feasibility Study (PFS) for the Koppamurra Project, together with
a maiden Ore Reserve estimate together with an updated Mineral Resource estimate (refer ASX announcements "Pre-
Feasibility Study and maiden Ore Reserve confirm Koppamurra as a compelling project" and "Maiden Ore Reserve
positions Koppamurra for development," both 25 June 2026).
The PFS confirms Koppamurra as a technically simple, low-capital, high-value development opportunity, underpinned
by shallow open-pit mining, rapid progressive rehabilitation, a simple heap leach flowsheet and offsite calcination to
produce a high-value Mixed Rare Earth Oxide (MREO) product.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Koppamurra Project Location
The PFS delivered very strong project economics that firmly establish Koppamurra as one of the most compelling rare
earth development opportunities in Australia:
• Exceptional returns on attractively low capital spend: Base Case after-tax NPV₈ of A$858 million and after-tax
IRR of 99% on initial capital expenditure (CAPEX) of just A$178 million — a capital efficiency ratio rarely seen in
the resources sector and a clear signal of the value embedded in this asset.
• Strategic exposure to high-value rare earths with rapid payback: Capital payback in just 0.9 years post-tax,
with annual production of Mixed Rare Earth Oxide (MREO) feedstock containing approximately 1,860 tonnes
of Total Rare Earth Oxides (TREO) including a strategically attractive, high value suite of magnet rare earths —
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
neodymium, praseodymium, dysprosium and terbium — along with yttrium, gadolinium, samarium and
lutetium. All are increasingly critical to Western supply chains, with most subject to Chinese export controls.
• Significant upside beyond the PFS mine plan: The PFS draws on a maiden Ore Reserve of 26Mt at 920ppm
TREO and processing capacity of 3Mtpa for an initial 12-year mine life. The broader resource and substantial
Exploration Target provide potential to materially extend mine life beyond the initial PFS case in a capital
efficient manner, with follow up drilling planned to expand the resource base.
Table 1 — Key Financial and Production Metrics — PFS Base Case
Metric Unit PFS Base Case
Processing Capacity Mtpa 3
Life of Operation (PFS mine plan) Years 12
Ore Reserve Mt 26
Average TREO Feed Grade ppm 920 (Ore Reserve)
TREO / MREO Recovery % 68
Average Annual Production (TREO) t 1,860
Initial CAPEX A$M 178
Operating Cost (ex-royalties) US$/kg TREO 34.14
All-In Sustaining Cost (AISC) US$/kg TREO 38.32
Post-Tax NPV₈ A$M 858
Post-Tax IRR % 99
Post-Tax Payback (from first production) Years 0.9
The PFS economic evaluation is as at Financial Investment Decision (“FID”) and payback period is from first production.
Base Case pricing uses the average of two independent market analysts, Adamas Intelligence and Argus Media (Q2 2026 long-term Western forecasts to 2040).
The Maiden Ore Reserve for Koppamurra comprises 26 Mt at 920 ppm TREO (Probable), converted directly from
Measured and Indicated Mineral Resources; approximately 22% higher grade than the 751 ppm TREO global Mineral
Resource average. The updated global Mineral Resource of 243 Mt at 751 ppm TREO represents an increase of ~7 Mt
on the September 2024 estimate (achieved on no additional drilling, reflecting improved geological modelling and re-
domaining of the resource to more accurately isolate calcium-rich material). Approximately 47% of the Mineral
Resource is classified as Measured or Indicated.
Table 2 — Ore Reserve Estimation as at 25 June 2026
Approximately 25% of TREO within the Mineral Resource comprises magnet rare earth elements (neodymium,
praseodymium, dysprosium and terbium); dysprosium and terbium together account for ~3% of TREO. Yttrium,
gadolinium, samarium and lutetium are also present and are, together with dysprosium and terbium, subject to China's
expanded rare earth export controls.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Capital and Operating Costs
Initial capital expenditure is estimated at A$178 million (inclusive of ~25% / A$35 million contingency), comprising the
processing plant (A$77m), site infrastructure and services (A$48m), temporary facilities (A$4m) and owner's costs
(A$14m). Operating costs are estimated at A$96 million per annum (US$34.14/kg TREO ex-royalties), with mining and
processing accounting for approximately 45% and 51% of total operating cost respectively. Ore amenable to heap-leach
processing means the Project is capital-light relative to peer rare earth developments and is not materially sensitive to
changes in capital cost, reflecting the low initial capital requirement.
Koppamurra Process Flowsheet.
Model Birdseye View of Processing Plant.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Path to Production
Following the PFS, AR3 will progress the Project in parallel across several workstreams: submission of the Mining Lease
Application (targeted 2026); pilot plant operations at ANSTO's Sydney facility, generating product samples for customer
qualification and engineering data for the Definitive Feasibility Study (DFS); product qualification and offtake discussions
with strategic partners; further drilling to support conversion of mineral resource categories to a higher degree of
confidence, including supporting additional Ore Reserves; and initiation of the DFS itself. No binding commitment for
development funding has been received as at the date of this report; the Company is assessing a range of funding
options including equity, debt, strategic partner investment, offtake-linked financing and government funding, and
there is no certainty that funding will be secured on acceptable terms, or at all.
ANSTO Pilot-Scale Facility Officially Opened
During the quarter, the Federal Government officially opened ANSTO's new critical minerals piloting facility in Sydney,
with AR3 confirmed as the first industry partner to utilise the facility (refer ASX announcement "ANSTO's new critical
minerals facilities opened; AR3 pilot processing to commence in June 2026 - 13 May 2026"). The Hon Madeleine King
MP, Minister for Resources and Minister for Northern Australia, and ANSTO Chief Executive Officer Shaun Jenkinson
attended the opening alongside AR3 Managing Director and CEO Travis Beinke.
Travis Beinke, Managing Director & CEO of AR3 attending the official opening of ANSTO’s new critical minerals processing facilities. From left to right: Shaun
Jenkinson, CEO ANSTO, Travis Beinke, MD & CEO Australian Rare Earths, The Hon Madeleine King MP, Minister for Resources and Minister for Northern
Australia, Michael Quigley, Board Chair ANSTO, Cr Jack Boyd, Mayor Sutherland Shire Council
Approximately 30 tonnes of Koppamurra ore, prepared and transported to Sydney during the quarter, is on-site and
ready for processing through a continuous pilot-scale circuit, with pilot-scale operations commencing in August 2026.
The pilot program will process Koppamurra ore to produce a Mixed Rare Earth Oxide (MREO) product, with samples to
be provided to potential customers to support offtake and product qualification discussions, and to generate
engineering data to inform the DFS. The program is co-funded under AR3's $5 million IPCM grant.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Mining Lease and Regulatory Approvals
Preparation of the Mining Lease Application (MLA) remained on track during the quarter, with submission targeted in
2026. Baseline environmental studies, covering ecology (native vegetation, flora and fauna, scattered trees),
groundwater, stygofauna and sinkholes, are complete, building on the Scoping Report published by the South Australian
Department for Energy and Mining, which confirmed the regulatory pathway and scope of assessments required to
support the MLA.
Overland Project, South Australia
Overland is located in South Australia, widely regarded as one of the world's premier uranium jurisdictions, hosting the
only three currently operating uranium mines in Australia. AR3's uranium exploration continues against a supportive
macro backdrop of robust uranium prices, driven by expanding global nuclear power programs, energy security
imperatives and structural supply constraints.
Uranium Drilling Program Completed at Sedan
AR3 commenced its planned uranium drill program at the Overland Project on 29 April 2026, following arrival of the
drilling rig at EL7079 (refer ASX announcement "AR3 commences uranium drilling at Overland, South Australia" 29 April
2026). The program tested two priority sedimentary-hosted uranium target zones — the Western Flank Zone within the
Ettrick Formation and the Basal Sandy Unit — both identified through AR3's review of historic drilling data and
confirmed assay results from historic core hole C051 (refer ASX announcement "AR3 to recommence uranium drilling
at Overland in April 2026" 5 March 2026, and the Quarterly Activities Report for the three months ended 31 March
2026).
The program, comprising 22 aircore holes for a total of 1,280 metres, was completed across April and May 2026, testing
the continuity, thickness and lateral extent of mineralisation across the two target zones. Reporting of assay results
were pending as at 30 June 2026 — refer “Subsequent to the Quarter” below.
Rig on first location
Northern Queensland Rare Earths Projects
No activities were conducted over the Company's Queensland projects during the reporting period.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Financial Update
The Company completed the quarter with $4.6 million in cash as at 30 June 2026. AR3 continues to be supported by
the Australian Government's $5 million International Partnerships in Critical Minerals (IPCM) grant, which includes co-
funding of pilot-scale processing operations at ANSTO. As at 30 June 2026, total IPCM grant receipts stood at
$2.75million, with $2.1 million anticipated to be received in August 2026 and the balance of funds in early 2027, subject
to the achievement of agreed milestones.
Corporate Update
A General Meeting of shareholders was held on 21 April 2026 to seek shareholder ratification of placement shares and
approval for the issuance of options attached to the January 2026 placement. All resolutions put to the meeting were
approved by shareholders.
Following the release of the PFS and maiden Ore Reserve, together with pilot-scale MREO product samples expected
from ANSTO, the Company expects offtake discussions with strategic partners to accelerate, particularly among
Western customers seeking to secure rare earth feedstock rich in heavy and magnet rare earth elements outside of
China.
Travis Beinke, Managing Director and CEO, presented at the RIU Sydney Resources Round-Up held between 5 to 7 May
2026 at the Hyatt Regency Sydney. Mr Beinke presented on, 6 May 2026, providing investors with an update on the
Company's progress at the Koppamurra Rare Earths Project, alongside developments at the Overland Uranium Project
and AR3’s broader growth strategy. A copy of his presentation can be found here.
Subsequent to the Quarter
Identification of a new Niobium–Rare Earth Carbonatite System at Overland (8 July 2026)
On 8 July 2026, AR3 announced the identification of a new niobium–rare earth carbonatite mineral system at the
R254 prospect within its 100%-owned Overland Project, discovered during the Company's Sedan sedimentary-hosted
uranium drilling program (refer ASX announcement "Discovery of Niobium-Rare Earth Carbonatite System Identified
at Overland Project" 8 July 2026). Highlights of the exploration results include:
• Drill hole OV167 intersected a 19-metre interval of anomalous rare earth and niobium mineralisation from 86
metres to end of hole (105m), with the mineralised interval remaining open at depth.
• Significant intersection: 19m @ 0.61% Total Rare Earth Oxides (TREO), including 20%
Neodymium+Praseodymium oxides (NdPr) and 1.7% Dysprosium+Terbium oxides (DyTb) of the TREO, including
7m @ 0.56% TREO with 0.27% Nb₂O₅ from 86m (including 1m @ 1.0% TREO with 0.53% Nb₂O₅ from 87m), 3m
@ 1.16% TREO from 93m, and 9m @ 0.46% TREO from 96m.
• Pyrochlore — the principal niobium ore mineral in major niobium deposits globally — was identified through
petrographic and Scanning Electron Microscope (SEM) assessment of drill cuttings.
• OV167 was drilled above a large coherent magnetic anomaly, interpreted to potentially reflect Fe–Ti oxide
accumulation within basement rocks, and presents an immediate follow-up drilling target; AR3's current
interpretation is that OV167 may have intersected a sill or dyke-like expression of a larger, untested carbonatite
intrusive system.
• Follow-up work planned includes expanded geophysical modelling (gravity gradiometry and magnetics),
detailed petrographic and mineralogical assessment, and targeted drilling to test the extent of the carbonatite
system.
Cautionary Note: The Company cautions that the results are from a single drill hole; there is currently insufficient data to define a
Mineral Resource, and it is uncertain whether further exploration will result in the estimation of a Mineral Resource. Early-stage
results may not be representative of the overall target. However, the geological, geochemical and mineralogical characteristics of
OV167 support further systematic exploration of the R254 target.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Image: Drillhole Location Plan with Total Magnetic Intensity (TMI). South Australian regional total magnetic intensity images.
https://pid.sarig.sa.gov.au/dataset/mesac139
Image: Drillhole Location with W-E section plan and Total Magnetic Intensity (TMI). South Australian regional total magnetic intensity
images. https://pid.sarig.sa.gov.au/dataset/mesac139
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
W-E Section displaying downhole; lithology, gamma response (cps), assays for TREO, Niobium and Barium
The broader 22-hole, 1,280-metre Sedan drilling program — designed primarily to test the Western Flank Zone and
Basal Sandy Unit sedimentary-hosted uranium targets — continued to indicate anomalous uranium accumulations in
the sedimentary sequence; however, no significant uranium intersections were identified from this program.
Listing Rule 5.23 Disclosure
The Company confirms that it is not aware of any new information or data that materially affects the Exploration Results
and/or the estimates of Mineral Resources and Ore Reserves in this release, and in respect of the estimates of Mineral
Resources and Ore Reserves reported, that all material assumptions and technical parameters underpinning the
estimates continue to apply and have not changed.
In respect of the updated Mineral Resource, Ore Reserve and Exploration Target for the Koppamurra Project, the
Company confirms that it is not aware of any new information or data that materially affects the estimates included in
the relevant market announcements (ASX announcements dated 25 June 2026, “Pre-Feasibility Study and maiden Ore
Reserve confirm Koppamurra as a compelling project” and “Maiden Ore Reserve positions Koppamurra for
development”) and that all material assumptions and technical parameters underpinning those estimates continue to
apply and have not materially changed.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
List of Tenements
Tenement Location Commodity Project Jurisdiction
EL6509 Naracoorte Rare Earths Koppamurra SA
EL6613 Frances Rare Earths Koppamurra SA
EL6690 Keith Rare Earths Koppamurra SA
EL6691 Bordertown Rare Earths Koppamurra SA
EL6942 Wattle Range Rare Earths Koppamurra SA
EL6943 Tarpeena Rare Earths Koppamurra SA
EL007254 Apsley Rare Earths Koppamurra Victoria
EL007719 Minimay Rare Earths Koppamurra Victoria
EL008208 Lake Mundi Rare Earths Koppamurra Victoria
EL008254 Dartmoor Rare Earths Koppamurra Victoria
EL008435 Charam Rare Earths/HMS Koppamurra Victoria
EPM27952 Massie Creek Rare Earths Massie Creek QLD
EPM28169 Stones Creek Rare Earths Dalrymple QLD
EPM28168 Mt Wickham Rare Earths Dalrymple QLD
EPM28165 Riverside Rare Earths Dalrymple QLD
EPM28167 Burdekin Rare Earths Dalrymple QLD
EPM28166 Dalbeg Rare Earths Dalrymple QLD
EPM28872 Forty Mile Scrub Rare Earths Forty Mile Scrub QLD
EPM28901 Sandy Tate Rare Earths Sandy Tate QLD
EPM28902 Oaky Valley Rare Earths Oaky Valley QLD
EL7079 Fisher Uranium / Rare Earths/Nb Overland SA
EL7080 Blanchetown Uranium Overland SA
EL7081 Steinfeld Uranium Overland SA
EL7005 Sturt Vale Uranium Overland SA
EL7001 Warnes Uranium Overland SA
EL7003 Bunyung Uranium Overland SA
EL7055 Sturt Vale Uranium Overland SA
EL6678* Warnes Area Uranium Overland SA
EL6895^ Stockyard Plain Uranium Overland SA
EL7010 Wirrealpa Uranium Triggs Bore SA
EL7011 Moolawatana Uranium Hamilton Creek SA
1 – All tenements are 100% held by AR3 unless noted.
* EL is in the process of being transferred to AR3 with AR3 holding the sedimentary hosted mineralisation right.
^ Refer to ASX announcement 10 July 2025 regarding the acquisition of EL6895 with the transfer to AR3 subject to Ministerial consent pursuant to section
15AB of the Mining Act.
ASX ANNOUNCEMENT AUSTRALIAN RARE EARTHS
Metals for our future
Australian Rare Earths | ACN 632 645 302 | Level 10, 111 Gawler Place, Adelaide, SA 5000 | www.ar3.com.au
Capital Structure
Shares on issue: 256,074,545 fully paid ordinary shares.
Options on issue: 46,485,347 unlisted options, comprising:
• 1,500,000 exercisable at $0.37 and expiring on 26 November 2026
• 1,500,000 exercisable at $0.50 and expiring on 26 November 2026
• 1,550,000 exercisable at $0.50 and expiring on 2 December 2026
• 1,500,000 exercisable at $0.4739 and expiring on 20 December 2026
• 1,808,333 exercisable at $0.435 and expiring on 26 November 2027
• 3,000,000 exercisable at $0.325 and expiring on 26 November 2028
• 16,374,926 exercisable at $0.10 and expiring on 30 March 2029 (unless accelerated)
• 18,189,194 exercisable at $0.2775 and expiring 21 April 2029
• 1,062,894 exercisable at $0.00 and expiring on 30 September 2029
Appendix 5B Disclosures
AR3's accompanying Appendix 5B (quarterly cash flow report) includes an amount in item 6.1 which constitutes
executive remuneration and non-executive director fees for the quarter. It includes Options Exercises made by Directors
in June.
During the period, the Company spent approx. $1.740m on exploration activities, including direct costs associated with
the Koppamurra exploration and development programs, which included, drilling, geochemical assays, metallurgical
test work. This figure also includes allocation of wages directly attributed to specific exploration and development
activities.
The Board of AR3 authorised this announcement to be released to the ASX.
For further information please contact:
Australian Rare Earths Limited
Travis Beinke
Managing Director and CEO
T: 1 300 646 100
Media Enquiries
Jessica Fertig
Tau Media
E: jessica@taumedia.com.au
We encourage shareholders and followers to ask any questions here: https://investorhub.ar3.com.au
About Australian Rare Earths Limited
Australian Rare Earths (AR3) is a diversified critical minerals company, strategically positioned to meet the growing
global demand for uranium and rare earth elements:
• AR3's Koppamurra Rare Earths Project in South Australia and Victoria is a significant deposit of light and heavy
rare earths, now underpinned by a Pre-Feasibility Study and maiden Ore Reserve, and supported by the
Australian Government through a $5 million grant to accelerate development. AR3 is progressing toward a
Definitive Feasibility Study and pilot-scale demonstration production at ANSTO's Sydney facility, solidifying its
role as a potential new source of new supply to diversify global rare earth feedstocks for the clean energy
transition.
• AR3's large ~8,000 km² Overland Uranium Project in South Australia shows strong uranium discovery potential,
with drilling also identifying a new niobium–rare earth carbonatite exploration target.
With strategic projects as well as strong government support, AR3 is well placed to capitalise on significant growth in
the critical minerals market.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Australian Rare Earths Limited
ABN Quarter ended (“current quarter”)
73 632 645 302 30 June 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
1. Cash flows from operating activities
8 29
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs - net of allocations to
capitalised exploration assets
(141) (1,010)
(e) administration and corporate costs (375) (935)
1.3 Dividends received (see note 3)
1.4 Interest received 58 157
1.5 Interest and other costs of finance paid -
1.6 Income taxes paid -
1.7 Government grants and tax incentives –
R&D Tax incentive
- 618
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(450) (1,141)
2. Cash flows from investing activities
-
2.1 Payments to acquire or for:
(a) entities
(b) tenements -
(c) property, plant and equipment
(d) exploration & evaluation (1,740) (7,971)
(e) investments - -
(f) other non-current - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment (9) (17)
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - 2,010
2.6 Net cash from / (used in) investing
activities
(1,749) (5,978)
3. Cash flows from financing activiti