Amended - Flowsheet Update for Koppamurra
Released
Released
Announcement PDF
Amendment
2 April 2024
Australian Rare Earths Limited (ASX: AR3) announces an amendment to its Flowsheet Update for Koppamurra
Outlines Low Capital Development Pathway.
The amendment is to page 11, to include a Competent Persons Statement as shown below and the
inclusion of JORC table 1 section 1 to the report appendices.
Competent Person’s Statement
The information in this report that relates to Exploration results is based on information compiled by
Australian Rare Earths Limited and reviewed by Mr Rick Pobjoy who is the Technical Director of the Company
and a member of the Australian Institute of Mining and Metallurgy (AusIMM). Mr Pobjoy has sufficient
experience that is relevant to the style of mineralisation, the type of deposit under consideration and to the
activities undertaken to qualify as a Competent person as defined in the 2012 edition of the “Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Pobjoy consents to the
inclusion in this report of the matters based on this information in the form and context in which it appears.
The Secretary of AR3 has authorised this announcement for release to the ASX.
For further information please contact:
AR3
Travis Beinke
Chief Executive Officer
T: 1 300 646 100
Media Enquiries
Jessica Fertig
Tau Media
E: jessica@taumedia.com.au
02 April 2024
Flowsheet Update for Koppamurra Outlines
Low Capital Development Pathway
AR3 Identifies Progressive Heap Leaching Development Pathway
for Efficient Rare Earths Extraction at Koppamurra
Highlights:
•
Metallurgical testwork delivers high recoveries for Magnet Rare Earths (MRE) up to
72% (ranging from 43% to 72%).
•
Progressive heap leach development pathway offers lower capital and operating costs
compared to tank leach alternative.
•
Optionality for modular expansion to scale up production over time across the province.
•
Improved environmental sustainability characteristics:
o Very low water consumption
o Reduced power consumption
o Rapid, progressive rehabilitation techniques
•
Testwork also indicates lower gangue/impurity profile with higher rare earth in
solution characteristics through column leach, favouring this development approach
for an economically sustainable basis of development.
Australian Rare Earths Limited (ASX: AR3) is pleased to announce significant advancements in
the metallurgical testwork conducted on its Koppamurra rare earths project in South Australia.
These results have identified an improved development pathway (relative to previous tank slurry
leach studies) through a progressive heap leach and rapid rehabilitation approach. Specifically,
the metallurgical testwork on high-grade mineralised clays from Koppamurra has identified an
improved approach for efficient extraction of rare earths through on-site leaching using short
term heaps of the clay made alongside the mine pit.
The Australian Nuclear Science and Technology Organisation (ANSTO) is Australia’s leading
laboratory in ionic clay leaching and has assisted AR3 with its ongoing process flowsheet
development work.
Engage with this announcement at the AR3 investor hub.
AR3 Chief Executive Travis Beinke said:
“Over the past four months, we’ve achieved extremely promising results in Magnet Rare Earth
recoveries achieved through column leach test work with ANSTO. Combined with the high-grade
subsets of the Koppamurra rare earth resources, the results open up positive outcomes for a highgrade progressive heap leach and rapid rehabilitation development pathway at Koppamurra.
Much of our metallurgical testwork to-date has focused on a slurry leach development pathway,
which is consistent with the approach taken by most early-stage ionic clay projects in Australia
and Latin America. However, given the infancy of ionic clay projects outside of China, our team
decided to explore an alternate development pathway by investigating the leaching
characteristics of the Koppamurra clays under a heap leach approach.
The preliminary column leach results are extremely encouraging. These initial, unoptimised
results have demonstrated magnet rare earth recoveries that are comparable to, or even better
than, results previously achieved via slurry leach testwork at Koppamurra.
We’ve identified several potential advantages of a progressive heap leach development
approach. These include potentially lower initial capital and operating costs, and improvements
to the project’s environmental credentials, such as reduced water and power consumption.
Importantly, this approach is also expected to enhance the clay’s material handling
characteristics, consistent with sustainable, rapid and progressive rehabilitation of the land after
mining to return it to its former use.
Overall, this is a significant step forward for the technical and economic viability of the
Koppamurra project, especially at a time when western governments are increasingly committed
to developing alternative, sustainable supplies of the rare earths essential for the clean energy
transition and national security.”
ANSTO Metallurgical Column Leach Testwork
Metallurgical column leach testwork commenced at ANSTO in December 2023. The Koppamurra
ore material generated from the Trial Pit operations 1 and from composite ‘variability’ samples
have responded positively to agglomeration and percolation techniques which could be applied
at larger scales in a progressive heap leach application and taken forward as a development
pathway for the environmentally and economically sustainable multi-generational production of
rare earths from the Koppamurra rare earths province.
The material, after column leaching, has shown favorable geochemical and geotechnical
characteristics for the environmentally sustainable, rapid, progressive rehabilitation techniques
planned for Koppamurra rare earth production. Detailed materials handling and geochemical
stability assessments are being made of the material from these current tests and are planned
for subsequent tests to ensure an environmentally sustainable operation at Koppamurra can be
achieved.
Samples provided for column leach test work include samples taken from a range of locations
and bench heights within the Trial Pit, and from the collation of drill hole cuttings representing
significant areas of aerial extent covering the existing Koppamurra Mineral Resource Estimate.
These Composite Samples (CP) derived from drillhole cuttings represent potential variability of
1 Refer to ASX release 11 April 2022 “Mining Trial Commences at Koppamurra”
the Koppamurra clay hosted rare earth resource and are key to demonstrating uniform recoveries
using a progressive heap leach approach across the deposit.
Composite drill hole cuttings masses totaled as follows:
CP3a
CP4a
CP5a
CP6a
CP10a
CP10b
100kg
40kg
70kg
30kg
40kg
20kg
The individual samples making up the Composites, CP’s 3a, 4a, 5a, 6a and 10a/10b are listed in
Appendix II. The CP locations are illustrated in Figure 1 with respect to the Mineral Resource
categories and AR3’s proposed Mine Lease Application boundary.
Figure 1: Composite sample locations for Column leach test work, with Column ID’s C1 through C6 (blue)
The favourable geochemical and geotechnical characteristics of the leached material can be
seen in the images below. They show that the competent, granular nature of the post-leach
material will favour an environmentally sustainable return of this neutralised material to the
excavated void, maintaining the previous geological/hydrological profile which will enable a rapid
return to previous land uses.
Figure 2: Column 1 clay in bucket post column test & material in column 2 post agglomeration, leaching, wash.
Next steps include testing samples from a range of additional locations within the current
Koppamurra Resource area, for variability assessments, and to increase the height of the test
columns to assess optimal heap geometries.
This work, along with ongoing optimisation of reagent consumption and gangue dissolution
characteristics, will be the focus of metallurgical testwork at Koppamurra over the next 3 to 6
months. Liquors extracted from the column testwork will also be assessed for impurity removal
requirements, and ultimately the preparation of additional Mixed Rare Earth Carbonate (“MREC”)
for customer assessments.
AR3 is working closely with NEO Performance Materials Inc. (“Neo”), a world-leader in the
production of rare earth permanent magnets and other rare earth products and whom with AR3
has a non-binding Memorandum of Understanding that provides for an offtake agreement for
Koppamurra initial production of a MREC. Importantly, Neo operates several rare earth
production facilities around the world, including one of the few western separation plants that
source MREC from third-party producers. Neo’s experience in providing input to MREC supply
continues to be invaluable to AR3.
Ore Variability
Key to next steps in optimising the application of a progressive heap leach approach at
Koppamurra is to identify optimal acid addition to the alkaline clay materials hosting rare earths
there. The alkaline nature of the host material along with variable calcium contents within the
sedimentary sequence are the main drivers for acid consumption during leaching of Koppamurra
ore. Variability testwork to date has shown a strong correlation between acid consumption,
gangue dissolution, rare earth recovery, and calcium contents of the samples.
Testwork has been applied in such a way as to minimise the number of variables being considered
at one time. Columns 1,2 & 3 all used the same sample material – derived from the 2022 Test Pit
location - and had varying amounts of acid addition and leach solution pH (1.5 & 2.2). Whereas
columns 4, 5 & 6 had variable samples – derived from drill cuttings – with fixed acid addition and
leach solution pH (2.2).
Testwork Results
The testwork was undertaken at ANSTO, the leading laboratory in the metallurgical recovery
assessment of clay hosted rare earths in Australia and globally outside of China. ANSTO has
brought its wide-ranging experience and expertise to bear on the challenge of sustainable rare
earth recovery from clays and delivered this exciting new development in the metallurgical
treatment of Koppamurra ore.
The achievement of these results from the very first pass of this approach has been a significant
milestone in the future development of Koppamurra. While much testwork remains to be
undertaken to optimise this approach, these initial results have been encouraging.
The initial approach has been to apply the reagents to the ore for column leaching in much the
same recipe that had been applied for successful rare earth recovery in a slurry leach. Very good
recoveries have been achieved in the column using this initial recipe. Treatment of temporary
ore heaps through agglomeration and percolation has further advantages over a slurry leach
approach, including:
o
o
o
o
minimal water consumption
reduced power consumption
lower gangue dissolution relative to the rare earth concentration in solution
better materials handling characteristics
These attributes offer scope for further significant refinement and optimisation of the process
going forward.
Figure 3: Column’s 3 through 6 at ANSTO’s facility
Al
Fe
Si
Smectite
Index (2)
Tb
Assay
Ca % wt.
Dy
wt. %
> 75 micron
Pr
Magnet
Rare
Earths
(MRE)
General
Characterisation
Days under leach
Nd
Gangue Dissolution
(Gangue/ REE ratio) (1)
Target Feed
pH
Recovery
TREO Grade
Column /
Sample
Total Acid Addition
Table 1: Column Leach Summary
ppm
%
%
%
%
%
kg/t
%
%
m2/g
C1 – Trial Pit
71.2
75.9
64.8
66.3
72.0
2.57
0.67
0.18
1.5
62.3
31
(121/345/410)
C2 – Trial Pit
1,636
9.1
1.27
296
68.5
72.7
62.0
66.0
69.5
1.93
0.13
0.18
2.2
46.5
31
(121/345/410)
C3 – Trial Pit
*
*
*
43.8
48.7
32.0
33.0
43.3
0.05
0.01
0.17
2.2
29.3
32
(121/345/410)
C4 – Resource
Composite
936
41.7
40.9
51.9
44.5
42.8
2.14**
0.04**
0.30**
2.2
44.9
18
33.0
1.65
410
CP03a
C5 – Resource
Composite
1,060
42.4
41.9
44.0
38.5
42.5
0.74**
0.01**
0.20**
2.2
45.0
18
15.9
2.06
310
CP04a
C6 – Resource
2.12***
1.39***
0.18***
Composite
1,340
45.5
43.6
50.9
45.3
45.8
2.2
44.9
17
14.6
1.06
254
CP10a
(1) Gangue Dissolution (Gangue/REE Ratio) = N/ TRE+Y, where N = Al, Fe, Si – day of measure is the last day of data from ANSTO
* Day 27 used for TREY / Gangue ratio, as the last assays for Gangue is day 27 for Column C3.
** Day 11 used for TREY / Gangue ratio, as the last assays received from laboratory for Gangue is day 11 for Column C4 and C5 – to be updated
in the future releases.
*** Day 10 used for TREY / Gangue ratio, as the last assays received from laboratory for Gangue is day 10 for Column C6 – to be updated in
future releases.
(2) Methylene Blue Surface Area – assuming all smectite dominating MB surface area is in the <45micron fraction [m2/g <45micron basis]
62.3
100
3.0
90
2.5
80
Recoveries %
70
2.0
60
50
29.3
1.5
40
1.0
30
20
Gangue/REE Ratio
46.5
0.5
10
0
C1
C2
0.0
C3
Columns
Nd
Pr
Dy
Tb
Al/REE
Fe/REE
Si/REE
Total Acid Addition (kg/t)
Figure 4: Rare earth recoveries for Columns 1 through 3, showing Gangue dissolution characteristics (Al / Fe / Si) with
respect to overall acid addition
100
3.0
44.9
90
45.0
44.9
Recoveries %
70
2.0
60
50
1.5
40
1.0
30
20
Gangue/REE Ratio
2.5
80
0.5
10
0
C4
C5
0.0
C6
Columns
Nd
Pr
Dy
Tb
Al/REE
Fe/REE
Si/REE
Total Acid Addition (kg/t)
Figure 5: Consistent rare earth recoveries for Columns 4 through 6, showing gangue dissolution characteristics (Al / Fe / Si)
with respect to ore variability at constant acid addition of 45kg/t of Ore. Notable here is the relatively high gangue dissolution
for samples that received more than the optimal acid addition, based on their calcium contents (i.e. C4 & C6)
50
12.0
C6 Ca%:1.06
40
10.0
35
8.0
30
25
6.0
20
4.0
15
10
0
2.0
C4 Ca%:1.65
5
C5 Ca%:2.06
1
4
5
Free Acid (g/L)
Magnet Rare Earth Recoveries (%)
45
6
7
8
9
11
12
13
14
15
18
0.0
Days
C4 %MRE Recoveries
C5 %MRE Recoveries
C6 %MRE Recoveries
C4 - Free Acid
C5 - Free Acid
C6 - Free Acid
Figure 6: Magnet Rare Earth recoveries for columns C4 through C6 with free acid in leach liquors over time – illustrating
Calcium (Ca) contents of the variability samples as drivers of overall acid consumption
Flowsheet update: Progressive heap leach, high grade rare earths pathway
Additional drilling, assay results 2 and resources modelling undertaken at Koppamurra has
allowed for the identification of a high-grade rare earth subset of the broader Koppamurra
resources. These high-grade ore zones, and the application of temporary heap leaching
production pathways, will allow for scalable, efficient production of rare earths with staged
satellite developments enhancing the favorable environmental outcomes from a development of
this type.
A conceptual project process flowsheet is provided at Figure 7. Some of the design features and
resulting advantages for the Koppamurra project with a progressive heap leach pathway
compared to a slurry leach are as follows:
Design Features:
•
•
•
High-grade satellite mine sites with temporary heap pads located at the edge of the
satellite mine void;
The extracted top soil and overburden material will be temporarily set aside ready to be
placed back in the mine void after rare earths have been harvested from the clay and the
clay has been washed allowing for rapid and progressive rehabilitation of the land;
Water treatment equipment will be located near the temporary heap pads to facilitate
recycling and reuse of both water and reagents.
Design advantages include:
•
•
•
•
Potential for a significantly lower capital cost and reduced operating cost project;
Enables improved environmentally sustainable characteristics with;
o Very low water consumption
o Reduced power consumption
o Materials handling characteristics enabling environmentally sustainable, rapid,
progressive rehabilitation techniques
Testwork also indicates lower gangue/impurity profile with higher rare earth in solution
characteristics through column leach resulting in lower capital and operating cost;
Opportunity to easily expand and scale up production over time across the multigenerational province.
2 Refer to ASX release 19 December 2023 “New infill drilling assays reveal high grades and significant magnet rare earth content”
and ASX release 26 February 2024 “High-Grade mineralisation discovered North of Koppamurra MRE”
Figure 7: Koppamurra conceptual project flow sheet
Next Steps
Leaching Program
Column leaching of additional variability samples, C5a, C6a and C10b, (refer Figure 1) will be
conducted to establish the amenability of a range of ore conditions with respect to >75um coarse
fraction, smectite content, TREO head grade and calcium content in preparing the ore for heaping
and the optimal leaching chemistries that could be applied to them. Results from this variability
testwork will allow for future testwork to be designed and undertaken - dedicated to optimising
leach chemistries and ore preparation.
A column test applying the material and leach chemistry used in column C2 will be applied to a
4m column to assess effects of raising the height of the heap to potential operating heap
geometries.
Water Treatment/Recycling
Water treatment processes applied to the leach solutions and for the recycle of water and
reagents is being assessed at desktop level and will ultimately be tested through the application
of reverse osmosis, nano filtration and ultra filtration in a comprehensive test work program to
evaluate and select a process for the economic recovery of rare earth elements from the clay
hosted deposit at Koppamurra.
Impurity Removal
Following the leaching program, impurity removal optimisations will be performed to improve the
rejection of deleterious elements such as aluminium, iron, silica, whilst maximising the recovery
of the rare earths. The testwork will aim to evaluate impurity removal conditions including pH,
alkali type, temperature, and residence time.
Previous successful impurity removal testwork undertaken by AR3 will now be applied to the
much higher-grade rare earths in solution derived from the column leaches which also have lower
impurity to REE in solution ratios. Impurity removal steps in the production of marketable mixed
rare earth concentrates are further enhanced by lower gangue/REE ratios and can generate lower
REE losses through that process.
Rare Earth Precipitation
Following the impurity removal program, rare earth precipitation tests will be performed to
generate a saleable rare earth product. The testwork will evaluate the type of precipitation agent,
pH, temperature, residence time, % solids and solid liquid separation performance.
The announcement has been authorised for release by the Board of Australian Rare Earths Limited.
For further information please contact:
Australian Rare Earths Limited
Media Enquiries
Travis Beinke
Jessica Fertig / Genna Bower
Chief Executive Officer
Tau Media
T: 1 300 646 100
E: info@taumedia.com.au
Engage and Contribute at the AR3 investor hub: https://investorhub.ar3.com.au/
Competent Person’s Statement
The information in this report that relates to metallurgical results is based on information compiled by
Australian Rare Earths Limited and reviewed by Mr. Jon Weir who is the Technical Director of Wallbridge
Gilbert Aztec and a member of the Australian Institute of Mining and Metallurgy (AusIMM). Mr. Weir has
sufficient experience that is relevant to the metallurgical testing which was undertaken to qualify as a
Competent Person as defined in the 2012 edition of the “Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves”. Mr. Weir consents to the inclusion in this report of the
matters based on this information in the form and context in which it appears.
The information in this report that relates to Exploration results is based on information compiled by
Australian Rare Earths Limited and reviewed by Mr Rick Pobjoy who is the Technical Director of the
Company and a member of the Australian Institute of Mining and Metallurgy (AusIMM). Mr Pobjoy has
sufficient experience that is relevant to the style of mineralisation, the type of deposit under
consideration and to the activities undertaken to qualify as a Competent person as defined in the 2012
edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves”. Mr Pobjoy consents to the inclusion in this report of the matters based on this information
in the form and context in which it appears.
About Australian Rare Earths Limited
Australian Rare Earths is committed to the timely exploration and development of its 100% owned,
flagship Koppamurra Project, located in the new Koppamurra rare earths Province in southeastern
South Australia and western Victoria. Koppamurra is a prospective ionic clay hosted rare earth deposit,
uniquely rich in all the elements required in the manufacture of rare earth permanent magnets which
are essential components in electric vehicles, wind turbines and domestic appliances. In addition, AR3
is actively reviewing other potential prospective areas which may also host ionic clay hosted rare earth
deposits throughout Australia.
The Company is focused on executing a growth strategy that will ensure AR3 is positioned to become
an independent and sustainable source of rare earths, playing a pivotal role in the global transition to a
green economy.
https://investorhub.ar3.com.au/link/Leovpy
JORC Table 1 – Section 1
Criteria
Sampling
techniques
Section 1 Sampling Techniques and Data
Explanation
Comment
Nature and quality of
RC Aircore drilling methods were used obtain
sampling (e.g., cut channels,
samples from the October-December 2021,
random chips, or specific
February-April 2022, September-December 2022
specialised industry standard February- June 2023, and October-December 2023
measurement tools
drilling programs.
appropriate to the minerals
under investigation, such as
The following information covers the sampling process:
down hole gamma sondes, or
• All air core samples were collected from the
handheld XRF instruments,
rotary splitter mounted at the bottom of the
etc). These examples should
cyclone using a pre-numbered calico bag and
not be taken as limiting the
plastic UV sample bag. The samples were
broad meaning of sampling.
geologically logged at 1 m intervals using the
Include reference to
marked calico sample which averaged ~1.5
measures taken to ensure
kg in mass.
sample representivity and
• A handheld Olympus Vanta XFR Analyser was
the appropriate calibration
used to assess the geochemistry of the air
of any measurement tools or
core samples in the field. The XRF analysis
systems used. Aspects of the
provided a full suite of mineral elements for
determination of
characterising
the lithological units.
mineralisation that are
• XRF readings were downloaded from the XRF
Material to the Public
Analyser at the end of each day and uploaded
Report. In cases where
‘industry standard’ work has
to the Australian Rare Earths Azure Data
been done this would be
Studio database.
relatively simple (e.g.,
• Field duplicates were taken at a rate of
‘reverse circulation drilling was
• ~1:34 and inserted blindly into the sample
used to obtain 1 m samples
batches.
from which 3 kg was pulverised
to produce a 30 g charge for fire • At the laboratory, the samples were oven
dried at 105 degrees for a minimum of 24
assay’). In other cases, more
hours and secondary crushed to 3 mm
explanation may be required,
fraction and then pulverised to 90% passing
such as where there is coarse
75
µm. Excess residue was maintained for
gold that has inherent sampling
storage while the rest of the sample placed in
problems. Unusual commodities
8x4 packets and sent to the central weighing
or mineralisation types (e.g.,
submarine nodules) may
laboratory. The samples were submitted for
warrant disclosure
analysis using XRF-ICP-MS method.
of detailed information.
• A laboratory repeat was taken at ~ 1 in 21
samples;
• Commercially obtained standards were
inserted by the laboratory at a rate of ~ 1 in 9
into the sample sequence.
Mechanical excavation techniques were applied
to the recovery of samples from the area of AR3’s
Trial Pit. Trial Pit samples were taken from a
number of discrete locations within the pit,
nominally 1m wide x 1m long x 0.5m deep.
Material from these locations were loaded into a
dump truck by an excavator and taken to a
laydown site for assessment.
Criteria
Section 1 Sampling Techniques and Data
Explanation
Comment
Up to 5 x dump truck piles of material from each
discrete location were dumped on the laydown.
Up to 12 x bulka bags were filled from those (up
to) 5 x piles of material and each was provided
a unique Bulka Bag # which referenced a Location
and sample pile number. Eg C2L1aP3 (C2 - cut
bench 2, L1a – location 1a, P3 – pile 3).
Samples provided for column leach testwork were
sourced from Trial Pit Locations;
C2L1aP3, Bulka Bag #146
C2L3P2, Bulka Bag #121
C4L4P5, Bulka Bag #410
C4L4P2, Bulka Bag #345
Samples were collected from the Bulka bags and
placed into 20 litre buckets for transfer to ANSTO
for testwork.
Criteria
Drilling
techniques
Explanation
Comment
Drill type (e.g., core, reverse
• Drilling was completed using a Mcleod or
circulation, open- hole
Wallis air ore drill rig (Landcruiser 6x6 or
hammer, rotary air blast,
similar) for the drilling.
auger, Bangka, sonic, etc) and • Aircore drilling is a form of reverse circulation
details (e.g., core diameter,
drilling where the sample is collected at the face
triple or standard tube, depth
and returned inside the inner tube. The drill
of diamond tails, facecuttings are removed by injection of compressed
sampling bit, or other type,
air into the hole via the annular area between
whether core is oriented and if
the inner tube and the drill rod.
so, by what method, etc).
• Aircore drill rods used were 3 m long.
• NQ diameter (76 mm) drill bits and rods
were used.
• All aircore drill holes were vertical with
depths varying between 2 m and 36 m.
Drill
sample
recovery
Method of recording and
•
assessing core and chip sample
recoveries and results assessed.
Measures taken to maximise
sample recovery and ensure
representative nature of the
samples.
•
Whether a relationship exists
between sample recovery and
grade and whether sample bias
may have occurred due to
preferential loss/gain of
fine/coarse material.
•
•
•
•
•
Drill sample recovery for aircore is monitored
by recording sample condition descriptions
where ‘Poor’ to ‘Very Poor’ were used to
identify any samples recovered which were
potentially not representative of the interval
drilled.
A comment was included where water
injection was required to recover the sample
from a particular interval. The use of water
injection can potentially bias a sample and
very little water injection was required during
this drilling program.
No significant loses of samples were observed
due to the shallow drilling depths (<36 m).
The rotary splitter was set to an approximate
20% split, which produced approximately 1.5
kg sample for each meter interval.
The 1.5 kg sample was collected in a prenumbered calico bags and the remaining 80%
(5 kg to 8 kg) was collected in plastic UV bags
labelled with the hole number and sample
interval.
At the end of each drill rod, the drill string is
cleaned by blowing down with air to remove
any clay and silt potentially built
up in the sample pipes and cyclone.
No relationship exists between sample
recovery and grade.
Criteria
Logging
Explanation
Comment
Whether core and chip
• All aircore samples collected in calico bags
samples have been
were logged for lithology, colour, cement
geologically and
type, hardness, percentage rock estimate,
geotechnically logged to a
sorting, and any relevant comments such as
level of detail to support
moisture, sample condition, or vegetation.
appropriate Mineral Resource
• Geological logging data for all drill holes was
estimation, mining studies
qualitatively logged onto Microsoft Excel
and metallurgical studies.
spreadsheet using a Panasonic Toughbook
Whether logging is qualitative
with validation rules built into the
or quantitative in nature. Core
spreadsheet including specific drop- down
(or costean, channel, etc)
menus for each variable. The data was
photography.
uploaded to the Australian Rare Earths Azure
The total length and percentage
Data Studio database.
of the relevant intersections
logged.
• Every drill hole was logged in full and logging
was undertaken with reference to a drilling
template with codes prescribed and guidance
to ensure consistent and systematic data
collection.
Subsampling
techniques
and sample
preparation
If core, whether cut or sawn
and whether quarter, half or
all cores taken.
If non-core, whether riffled,
tube sampled, rotary split,
etc and whether sampled
wet or dry.
For all sample types, the nature,
quality, and appropriateness of
the sample preparation
technique.
Quality control procedures
adopted for all sub-sampling
stages to maximise
representivity of samples.
Measures taken to ensure that
the sampling is representative
of the in- situ material
collected, including for
instance results for field
duplicate/second-half sampling.
Whether sample sizes are
appropriate to the grain size of
the material being sampled.
• 1 m aircore sample interval were
homogenised within the cyclone and the
rotary splitter was set to an approximate
20% split producing around 1.5 kg sample for
each metre interval.
• The 1.5 kg sample was collected in a prenumbered calico bag and the 80% (5 kg to 8
kg) portion was collected in plastic UV bags
labelled with hole identity and interval.
• Duplicates were generally taken within the clay
lithologies above the basement as this is the
likely zone of REE enrichmen