Annual Report to shareholders
Released
Released
Announcement PDF
SECURING
AUSTRALIA'S
ENERGY
TRANSITION
METALS
2026 Annual Report
2
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
3 | Australian Rare Earths 2026 Annual Report
Chairman’s Letter 4
CEO’s Letter 8
Operations Review
Diversified Project Portfolio 11
Koppamurra Project 12
Pre-Feasibility Study (PFS) 14
Maiden Ore Reserve 16
2026 Mineral Resource Estimation 18
Exploration Target 20
Heap Leaching Mining Method 22
Metallurgical Testwork and Process Development 24
Uranium Portfolio 26
2026 Drilling Program and New Uranium Targets 28
Niobium–Rare Earth Carbonatite Discovery 30
Australian Rare Earths Tenement Interests 33
Directors’ Report 34
Remuneration Report (Audited) 44
Auditor’s Independence Declaration 55
Financial Report
Statement of Profit or Loss and Other Comprehensive Income 58
Statement of Financial Position 59
Statement of Changes in Equity 60
Statement of Cash Flows 61
Notes to the Financial Statements 62
Consolidated Entity Disclosure Statement 80
Directors’ Declaration 81
Independent Auditor’s Report 82
Additional Information 86
Corporate Directory 89
Contents
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
Chairman's Letter
4
Dear Shareholders,
A year ago, we said that the strategic significance of rare earths had come into sharp focus. Over the 2025–2026 financial
year, that shift has moved from sentiment to substance. Chinese export controls have widened, and in response, other
governments have stood up strategic reserves and procurement frameworks. The world's reliance on a single-country
supply chain for the magnets that power everything from electric vehicles to wind turbines and defence systems has
become a mainstream policy concern rather than a specialist one.
5 | Australian Rare Earths 2026 Annual Report
Government is no longer a passive observer of this sector;
it is an active participant in de-risking projects.
"
"
And there’s a growing realisation of the similar exposure
to supply chain risk in other rare earth elements such as
yttrium and the non-magnet heavy rare earths, essential
to a range of other industrial and electronic applications.
Against that backdrop, Australian Rare Earths (AR3) has
converted years of testwork and drilling into a defined
development case. The Koppamurra Rare Earths Project
progressed to a Pre-Feasibility Study (PFS) and maiden
Ore Reserve, with the PFS’ central case presenting a
post-tax net present value of $858 million and a payback
period, from first production, of under a year on initial
capital of just $178 million.
Our Overland Uranium Project delivered further
systematic drilling and, in the closing weeks of the year,
an early-stage discovery of carbonatite with elevated
concentrations of niobium and rare earth elements,
opening a new avenue of value for the project. We
are, in short, in a stronger position today than the
macro tailwinds alone would suggest (and the tailwinds
themselves have strengthened).
The Macro Context
China's export restrictions on rare earth elements, first
announced in April 2025, expanded during the year to
capture a wider basket of elements, including yttrium,
gadolinium, samarium and lutetium in addition to
the magnet rare earths dysprosium and terbium. For
Western manufacturers of magnets, defence systems
and clean energy technology, this has sharpened an
uncomfortable truth: heavy and magnet rare earths are
supplied almost exclusively from Chinese-controlled
sources, and that concentration is now a live commercial
and national security risk rather than a theoretical one.
Koppamurra's product basket, weighted toward these
elements, sits directly in the path of the diversification
response that Western customers and governments are
now pursuing.
In Australia, the policy intent we described a year
ago has become policy in practice. Rare earths are
now among the first minerals named for inclusion in
the Federal Government's Critical Minerals Strategic
Reserve, and AR3's $5 million grant under the Australian
Government's International Partnerships in Critical
Minerals program (of which $2.75 million had been
received by the financial year end) has directly funded
metallurgical testwork and co-funded our pilot-scale
processing program with the Australian Nuclear Science
and Technology Organisation (ANSTO).
Abroad, we have seen the US move from a one-off price
support deal to such deals being struck with several
others, Japan moving to strike a price support deal with
an established Australian producer, and the launch of
Project Vault as a private-sector led, US-EXIM backed
commercial stockpile. The US has actively sought to
corral countries toward a coordinated policy and pricing
response to foster new, diversified rare earths supply,
most notably through a February 2026 Critical Minerals
Ministerial of over 50 countries.
The G7 Leaders’ summit in France included an important
declaration of intent to reduce reliance on any non-G7
member for rare earths and permanent magnets supply
to below 60% by 2030, with an ambition to further lower
that reliance further to 50% as soon as possible.
We await to see how these pledges are converted into
concrete policy action, especially in Europe, but the
message is clear: Government is no longer a passive
observer of this sector; it is an active participant in
de-risking projects.
The uranium thematic playing out at Overland is a
parallel story. South Australia remains one of the world's
premier uranium jurisdictions, home to the only three
currently operating uranium mines in the country, and
our exploration there this year took place against a
backdrop of robust uranium prices driven by expanding
global nuclear power programs and energy security
imperatives. The new niobium-rare earth carbonatite
discovery identified late in the year adds a further,
unplanned dimension of upside to that ground. This
serves as a reminder that systematic, well-targeted
exploration can surface value beyond the commodity
originally being sought.
6
CHAIRMAN'S LETTER
AR3 continued to seek to shape rare earths industry
policy at home and abroad, and to lift our profile
among potential offtake partners. During the year, the
Company participated in the Rare Earth Mines, Magnets
and Motors Summit in Toronto, attended the opening
of a new rare earth processing facility in Estonia by our
technical partner Neo Performance Materials, and was
invited to join an Austrade-sponsored delegation of
Australian critical minerals companies to Washington
DC to engage with US administration officials on closing
critical minerals supply gaps.
These are not, by themselves, operational milestones,
but they matter: they are how projects like Koppamurra
become known to the governments, customers and
financiers who will ultimately determine which projects
get built.
Positioning AR3
for the Opportunity
Being the beneficiary of a favourable macro backdrop is
not the same as being positioned to capture it, and the
Board's focus this year has been on ensuring AR3 is the
latter. Koppamurra's combination of shallow open-pit
mining with rapid progressive rehabilitation, a proven
heap leach flowsheet and a comparatively low initial
capital requirement gives it a shorter, lower-risk
path to future production than many peer rare earth
developments; a genuine advantage when capital for
small-cap developers remains difficult to source.
In the here and now, being confirmed as the first
industry partner to access ANSTO's new pilot-scale
processing facility removed the need for AR3 to fund
and build its own pilot plant, saving time and capital at a
critical stage of the Project's development.
With the Pre-Feasibility Study and maiden Ore Reserve
now delivered, the task ahead is converting a well-
defined project into a funded, constructed one. Much
hard work still lies ahead, and the Board is realistic
about the work still required to reach a final investment
decision.
We believe the combination of a de-risked technical
case and a structurally tightening supply picture for
magnet and other heavy rare earths gives AR3 – and
Koppamurra's technical and economic case is now defined,
and Overland has added a promising new dimension.
"
"
South Australia - a genuine opportunity to be part of the
diversified, non-Chinese supply chain that governments
and customers are now actively seeking to build.
With Thanks
The Company's ability to fund its work this year owes
much to the continued support of our shareholders,
who backed a $6 million placement to institutional,
sophisticated and professional investors during the year,
and to the Australian Government, whose IPCM grant
funding has directly underwritten key testwork and
pilot milestones.
I thank our shareholders and the Australian Government
for their support, I thank my fellow directors for their
continued guidance, and I thank the AR3 team, led by
Managing Director Travis Beinke, for all the hard work
and technical ingenuity they have brought to a year of
substantial progress.
Conclusion
The themes that were emerging a year ago are now
well established: governments are active participants in
shaping critical minerals supply chains, and the strategic
value of non-Chinese heavy and magnet rare earth
supply has never been clearer.
Koppamurra's technical and economic case is now
defined, and Overland has added a promising new
dimension. As geopolitics, policy and market forces
continue to move in this sector's favour, we believe
AR3 is well placed to convert that opportunity into
shareholder value.
Yours sincerely,
Angus Barker
Chairman
Australian Rare Earths Limited
Outlook
OVER THE
YEAR AHEAD,
OUR PRIORITIES
ARE:
Progress pilot-scale
operations at ANSTO
and deliver Mixed Rare
Earth Oxide product
samples for customer
qualification and offtake
discussions.
Submit the Mining Lease
Application for Koppamurra
and continue the Definitive
Feasibility Study, targeted
for completion in 2027.
Advance project funding
discussions across a range
of options, ahead of a final
investment decision.
Follow up the niobium-rare
earth carbonatite discovery
at Overland with further
geophysics and drilling,
alongside continued
uranium exploration
across our expanded
tenure.
Maintain AR3's engagement
with government and
industry, in Australia and
internationally, to ensure
the Company continues to
benefit from the policy
momentum behind critical
minerals.
7 | Australian Rare Earths 2026 Annual Report
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
Chairman's Letter
Dear Shareholders,
In 2025–2026, Australian Rare Earths made substantial operational progress across our portfolio, advancing the
Koppamurra Rare Earths Project from metallurgical testwork through to a Pre-Feasibility Study (PFS) and maiden
Ore Reserve, while our Overland Uranium Project delivered further drilling results and, near year end, an unexpected
new discovery. It has been a year in which the technical foundations we have been building came together into a
defined, de-risked development case.
CEO's Letter
8
9 | Australian Rare Earths 2026 Annual Report
Operational Overview
At Koppamurra, we spent the first half of the year
progressing metallurgical testwork with ANSTO,
achieving magnet rare earth extraction rates of
approximately 70% from ore and establishing a viable,
low-technical-risk pathway from pregnant leach solution
through to a Mixed Rare Earth Oxide (MREO) product.
A step-change improvement in heap leach performance,
in which doubling the irrigation rate approximately halved
leach cycle times without any loss in recovery, materially
improved the Project's capital and operating cost profile.
That testwork underpinned the PFS and maiden Ore
Reserve we released in June 2026; a post-tax NPV of
A$858 million, a post-tax IRR of 99% and a payback
of under a year on initial capital of A$178 million, built
around a 26 Mt Ore Reserve at 920 ppm TREO and an
updated global Mineral Resource of 243 Mt at 751 ppm
TREO.
In parallel, we were confirmed as the first industry
partner to access ANSTO's new pilot-scale rare earth
processing facility in Sydney, avoiding the cost and time
of building our own pilot plant and by year end, had
approximately 30 tonnes of Koppamurra ore on-site and
ready for processing. We also made steady progress on
the regulatory path to production, with the Department
for Energy and Mining's Scoping Report and our own
baseline environmental studies supporting a Mining
Lease Application we intend to submit by the end of
calendar year 2026.
At Overland, we expanded our tenure to approximately
8,000 km² and completed 67 holes for approximately
6,370 metres of drilling across two campaigns during
the year. The first, completed in the second half of 2025,
confirmed a compelling ISR-amenable uranium target in
the north-western region of EL7001.
The second, drilled across newly granted tenure in April
and May 2026, tested two priority target zones defined
from a detailed review of historic drilling, and while it did
not return significant uranium intersections, the same
program led from samples in drill hole OV167, to the
discovery of a niobium-rare earth carbonatite mineral
system at the R254 prospect. That is an early-stage result
from a single hole, but the presence of pyrochlore and
grades up to 1.16% TREO and up to 0.53% niobium make
it a discovery we intend to follow up quickly.
Financial Overview
During the year, we raised approximately $6 million
via a placement to institutional, sophisticated and
professional investors, which together with $2.75 million
received at financial year end under our $5 million
Australian Government International Partnerships
in Critical Minerals grant, has funded our testwork,
technical and environmental studies and preparation
for our pilot program, while maintaining a disciplined
cost base.
I thank our shareholders for that continued support.
We are now assessing a range of options from equity,
debt, strategic partner investment, offtake-linked
financing and government funding, to support
Koppamurra through to a final investment decision
and ultimately through construction.
Outlook
Looking ahead, our focus shifts from defining
Koppamurra to advancing it.
We commenced pilot-scale operations at ANSTO
shortly after year end, to produce MREO product
samples for customer qualification and to support
offtake discussions, alongside submission of our
Mining Lease Application in 2026 and completion of
a Definitive Feasibility Study targeted for 2027.
At Overland, we will follow up the niobium-rare earth
discovery with further geophysics and drilling, while
continuing to test the broader uranium potential of
our expanded tenure position.
I thank the AR3 team for their commitment and technical
depth over the past year, and our shareholders for their
ongoing support. We are energised by the progress
made and confident in our ability to keep converting
technical results into project value.
Yours sincerely,
Travis Beinke
Managing Director and CEO
Australian Rare Earths Limited
Operations Review
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
10
11 | Australian Rare Earths 2026 Annual Report
During the 2025–2026 financial year, Australian Rare Earths Limited (AR3 or the Company) continued to advance its
diversified project portfolio, anchored by the Koppamurra Rare Earths Project in South Australia and Victoria and the
Overland Uranium Project in South Australia, together with a portfolio of early-stage uranium and rare earths interests
in South Australia and Queensland.
Koppamurra progressed during the year, advancing from metallurgical testwork through to a Pre-Feasibility Study
(PFS) and maiden Ore Reserve, released in June 2026, together with the first delivery of Koppamurra ore to a pilot-scale
processing facility.
Overland delivered further systematic drilling across an expanded tenure package, defined new uranium target zones
informed by historic drilling data and, in the closing weeks of the year, an early-stage discovery of carbonatite with
elevated concentrations of niobium and rare earth elements that represents a new exploration opportunity for the Project.
Diversified Project Portfolio
Massie Creek
Oaky Valley
Sandy Tate
Forty Mile Scrub
Dalrymple
Overland
Koppamurra
Hamilton Creek
Triggs Bore
Rare Earths
Uranium
Copper/Gold
Koppamurra Project
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
12
13 | Australian Rare Earths 2026 Annual Report
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
KOPPAMURRA
Naracoorte
Mount Gambier
Keith
Bordertown
Penola
Portland
Murray Bridge
ADELAIDE
SOUTH
AUSTRALIA
VICTORIA
50km
KOPPAMURRA
Naracoorte
Mount Gambier
Keith
Bordertown
Penola
Portland
Murray Bridge
ADELAIDE
SOUTH
AUSTRALIA
VICTORIA
50km
Rare Earths Project SA & Vic Overview
The Koppamurra Project is AR3's flagship ionic clay-hosted rare earths development, spanning tenure in South
Australia and western Victoria. During the year, the Project moved from metallurgical testwork to a fully defined
development case, culminating in a Pre-Feasibility Study and maiden Ore Reserve that confirm Koppamurra as
one of the more advanced ionic clay rare earths development projects in Australia.
Scale/Size 7,400km2
Exploration Licence area
Ownership 100%
Maiden
Ore Reserve
26Mt @ 920ppm TREO Magnet Rare
Earth~26% of TREO including strategically
valuable heavy Rare Earth Elements
(REE's) dysprosium & terbium ~3%; along
with yttrium, gadolinium, samarium and
lutetium, now subject to China's expanded
export controls
Mineral
Resource
243Mt @ 751ppm TREO and untapped
Exploration Target; significant scope for
a multi-decade operation as the project
scales
Offtake Neo Performance Materials (Non-binding
MOU for 50% offtake of stage 1)
Location &
Jurisdiction
~300km SE of Adelaide, in South Australia
and Victoria Australia: Low political risk;
South Australia: Pro-mining state
Access:
Road & Port
Within 8km of main highway with
established road to site; Shipping via
the Port of Adelaide ~380km from the
project site (or Portland)
Workforce &
Supporting
Infrastructure
Access to skilled workforce regionally
Drive in workforce with no requirement for
camp or airstrip due to project location
Water & Power Water
Recycling of water within the process
will provide for a low water consumption
project; to be sustainably sourced from
local aquifer
Power
Either onsite solution or connection to
existing infrastructure tenure
14
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
Key Production Outcomes Annual Average LOM
Ore Mined (Mt) 3 34.9
Strip Ratio (waste: ore) 1.5 1.5
Average TREO Feed Grade (ppm) 927 924
TREO Recovery (%) 68 100
MREO Recovery (%) 68 100
TREO (t) 1,860 21,937
Neodymium Praseodymium (NdPr) (t) 435 5,136
Terbium (t) 9 102
Dysprosium (t) 48 563
Samarium (t) 69 814
Gadolinium (t) 67 788
Yttrium (t) 238 2,807
Lutetium (t) 4 50
Pre-Feasibility Study (PFS)
The Pre-Feasibility Study (PFS) confirms the potential for the Project to be developed as a technically viable, long-life
rare earths project based on shallow open-pit mining, heap leach processing, rapid progressive rehabilitation and
offsite calcination to produce a saleable mixed rare earth oxide product for supply to customers with rare earth oxide
separation capabilities, either in Australia, the EU, U.S. or other suitable destinations.
The development case is underpinned by extensive drilling, metallurgical testwork, environmental studies and
engineering design work completed by AR3 and its specialist consultants. The study provides the technical foundation
for the next phase of project development, including Mining Lease Application (MLA) submission, pilot plant operation,
product qualification, offtake engagement and definitive feasibility work.
Staged expansion potential
Long term optionality beyond initial 12-years.
Highly attractive MREO production delivering meaningful quantities of a strategically critical suite of rare earths
PFS targeted Southern portion of resource to support area around initial Mining Lease Application
Scope for staged capital efficient expansion North to significantly increase mine life and production rates
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
PFS Highlights
HIGHLY
ATTRACTIVE
PRODUCT
High-value MREO
basket with exposure to
constrained heavy REE
markets; including rare
earths are increasingly
critical to Western
supply chains
LOW
TECHNICAL RISK
Shallow open pit mining,
simple heap leach
flowsheet and rapid
progressive rehabilitation
key driver of the project’s
robust economics
LONG-TERM
OPTIONALITY
BEYOND THE PFS
Maiden Ore Reserve
with initial 12-year mine
life and substantial
potential for a multi-
decade operation as
the project scales
TIER-1 AUSTRALIAN
JURISDICTION
Western customers
seeking rare earth
feedstock rich in heavies
that can be delivered
from allied nations with
speed to market
COMPELLING
ECONOMICS
A$858m
After-Tax NPV8
;
99% IRR;
~1 yr payback
CAPITAL-LIGHT
DEVELOPMENT
A$178 million with
capital efficiency ratio
of 4.8; a clear signal of
the value embedded
in the asset
15 | Australian Rare Earths 2026 Annual Report
16
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
Maiden Ore Reserve
In June 2026, Australian Rare Earths achieved a major milestone with the declaration of a maiden Ore Reserve for
the Koppamurra Rare Earths Project. The Probable Ore Reserve of 26 million tonnes at 920 ppm TREO, converted
from Measured and Indicated Mineral Resources, represents an important step in demonstrating the Project’s
development potential.
The maiden Ore Reserve provides a defined foundation
for mine planning and supports the outcomes of the
Pre-Feasibility Study. The study applied project-specific
Modifying Factors, including mining, processing,
metallurgical recovery, operating cost and pricing
assumptions. The Reserve is underpinned by the
updated Koppamurra Mineral Resource of 243 million
tonnes at 751 ppm TREO, highlighting both the scale
of the mineralised system and its potential for staged
development.
The Ore Reserve grade is approximately 22% higher
than the average grade of the global Mineral Resource,
reflecting the opportunity to prioritise higher-value
areas within the deposit during initial mine planning.
The rare earth basket includes a significant proportion
of magnet and heavy rare earth elements, including
neodymium, praseodymium, dysprosium and terbium,
which are critical inputs for high-growth applications
such as electric vehicles, wind turbines and defence
technologies.
The maiden Ore Reserve materially de-risks Koppamurra
and provides a strong platform for advancing approvals,
detailed design, financing discussions and future
development activities. Together with the broader
Mineral Resource and Exploration Target, it reinforces
AR3’s confidence in Koppamurra’s scale, quality and
long-term growth potential.
The maiden Ore Reserve was central to the Koppamurra
Pre-Feasibility Study, providing the mineable inventory
used to support the proposed mine plan, production
schedule, processing assumptions and financial
evaluation. Supported by project-specific Modifying
Factors, it gives AR3 a stronger basis for assessing
development scale, capital requirements, operating
costs and project economics.
Category Material BD TREO TREO -
CeO2
La2
O3
Ce
O2
Pr6
O11
Nd2
O3
Sm2
O3
Gd2
O3
Mt (g/cm3
) ppm ppm ppm ppm ppm ppm ppm ppm
Probable 26 1.6 920 602 141 324 43 167 33 32
Tb4
O7
Dy2
O3
Ho
2O3
Er2
O3
Eu2
O3
Tm2
O3
Yb2
O3
Lu2
O3
Y2
O3
U3
O8
ThO2
ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm
Probable 4.5 25 4.7 13 7.6 1.6 10 1.4 125 1.4 19
ORE RESERVE ESTIMATION AS AT 25 JUNE 2026
4
3
2
1
0
1,200
1,000
800
600
400
200
0
Inferred
Ore Grade
Indicated
Measured
LIFE OF MINE PRODUCTION TARGET: RESOURCE CATEGORY AND GRADE
Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12
MT TREO ppm
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
KOPPAMURRA PROJECT MINING SEQUENCE
17 | Australian Rare Earths 2026 Annual Report
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
2026 Mineral Resource Estimation
AR3 engaged the specialist consulting group Mineral Technologies to complete an update of the Koppamurra
geological block model and Mineral Resource Estimate in 2026. Importantly, the update was primarily focused on
improving the geological resolution and quality of the resource model, rather than simply incorporating additional
drilling.
The work built on the previous Mineral Resource
Estimate by integrating an improved geological and
metallurgical understanding of the ionic-adsorbed clay
mineralisation and its relationship with the underlying
limestone and associated gangue material.
A key improvement was the refinement of geological
domaining to provide greater resolution of the principal
REE-enriched ore zones and improved separation of
mineralised clay from material associated with the
limestone contact and sporadic weathered limestone
clasts.
The revised model defines Zone 3 as the principal
REE-enriched clay domain, while Zones 4 and 5 provide
additional geological resolution around the basal contact
and areas containing weathered limestone clasts.
This approach provides a more representative model of
the orebody and its associated gangue material, while
preserving the interpreted continuity of the primary
mineralised clay domain.
The revised geological domains were incorporated
into updated grade interpolation and bulk density
assignment, supported by domain-specific variography,
contact analysis, sectional interpretation and statistical
validation.
The resulting model provides improved definition of
ore-zone geometry, grade distribution and internal
geological variability, increasing confidence in the
Mineral Resource model and providing a stronger
foundation for mine planning, metallurgical evaluation
and staged technical development of the Project.
18
Naracoorte office and facility
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
Category Material BD TREO
TREO -
CeO2
MREO La2
O3
Ce
O2
Pr6
O11
Nd2
O3
Sm2
O3
Gd2
O3
Mt (g/cm3
) ppm ppm %TREO ppm ppm ppm ppm ppm ppm
Measured 0.9 1.6 773 502 25.1 125 271 36 135 27 25
Indicated 113 1.6 766 502 25.3 121 264 35 135 27 26
Inferred 130 1.6 737 486 25.3 121 251 34 130 26 24
Total 243 1.6 751 493 25.3 121 257 35 132 26 25
GLOBAL MINERAL RESOURCE ESTIMATE FOR THE KOPPAMURRA PROJECT 2026
Tb4
O7
Dy2
O3
Ho
2O3
Er2
O3
Eu2
O3
Tm2
O3
Yb2
O3
Lu2
O3
Y2
O3
U3
O8
ThO2
ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm
Measured 4 20 4 10 6 1 8 1 102 1 21
Indicated 4 20 4 10 6 1 8 1 106 2 19
Inferred 3 19 4 9 6 1 7 1 102 2 18
Total 4 19 4 10 6 1 8 1 104 2 19
19 | Australian Rare Earths 2026 Annual Report
Koppamurra 2026 Mineral Resource Statement (JORC 2012)
The Global Mineral Resource reported above a 325 ppm TREO-CeO2 (TREO minus cerium oxide) cut-off grade for the
Project is presented in the table below. This table conforms to guidelines set out in JORC Code (2012). The Koppamurra
project comprises a total Mineral Resource estimate of 243 Mt @ 751 ppm TREO and 493 ppm TREO- CeO2.
The Global Mineral Resource JORC Categories are specifically stated as:
Measured Mineral Resource of 0.9 Mt @ 773 ppm TREO and 502 ppm TREO-CeO2,
Indicated Mineral Resource of 113 Mt @ 766 ppm TREO and 502 ppm TREO-CeO2, and;
Inferred Mineral Resource of 130 Mt @ 737 ppm TREO and 486 ppm TREO-CeO2.
20
Exploration Target
The Koppamurra Project retains a significant Exploration Target across the northern and southern extents of the
Project, highlighting the substantial scale of the mineralised system beyond the current Mineral Resource. The
Exploration Target occurs predominantly in areas where drilling remains widely spaced, but where existing drilling
and downhole assay results demonstrate continuation of the geological setting that hosts the Koppamurra Mineral
Resource.
The potential quantity and grade of the Exploration
Target is conceptual in nature, as there has been
insufficient exploration undertaken to estimate a Mineral
Resource and it is uncertain if further exploration will
result in the estimation of a Mineral Resource.
A cut-off grade range of 225 ppm to 425 ppm TREO-
CeO2
was used to define a Global Exploration Target
range of (680 Mt @ 820 ppm TREO to 3620 Mt @ 540
ppm TREO) for the Koppamurra project area.
The Exploration Target covers large areas across the
project both north and south informed by limited drilling
and downhole assay results at this stage of project
development.
There remains an opportunity for the Exploration Target
material to be converted into the Mineral Resource
estimate upon the completion of additional aircore
drilling in these areas.
Over the next 2 years, AR3 expects to undertake further
drilling across priority areas of the defined Exploration
Target. The program is intended to progressively test
geological continuity and reduce drill spacing from the
current widespaced pattern to approximately 240 m
and, where warranted, 120 m, providing additional data
that may support future Mineral Resource estimation.
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
Material
Type
Zone Material BD TREO
TREO -
CeO2
MREO Dy2
O3
Tb4
O7
Nd2
O3
Pr6
O11
Mt (g/cm3
) ppm ppm ppm ppm ppm ppm ppm
Target 3 650 - 3120 1.6 560 -820 360 - 540 140 - 210 15 - 20 3 - 4 100 - 150 25 - 40
4 30 - 500 1.6 420 - 690 300 - 500 110 - 190 10 - 20 2 - 3 80 - 140 20 - 40
Total 680 - 3620 1.6 540 – 820 350 - 540 140 - 210 15 - 20 3 - 4 100 - 150 25 - 40
SUMMARY OF 2026 GLOBAL EXPLORATION TARGET
2026 KOPPAMURRA JORC CLASSIFICATION
SECURING AUSTRALIA'S ENERGY TRANSITION METALS
21 | Australian Rare Earths 2026 Annual Report
OPERATIONS REVIEW KOPPAMURRA RARE EARTHS PROJECT
TEMPORARY
HEAP
CLAY
PREPARATION
4-10m
RAPID
REHABILITATED
MINE VOID
SOIL / SUBSOIL
OVERBURDEN PLACEMENT
NEUTRALISED CLAY
Heap Leaching Mining Method
Australian Rare Earths is designing a staged, low impact mining approach, where small, higher grade areas are mined
one at a time rather than developing one large continuous site.
Heap leaching has been selected as the method for extracting the rare earths from the clay. This is a mature and well
understood extraction method. Temporary processing areas,